Notice (8): Trying to access array offset on value of type null [APP/View/Articles/view.ctp, line 115]
Notice (8): Trying to access array offset on value of type null [APP/View/Articles/view.ctp, line 115]
Notice (8): Trying to access array offset on value of type null [APP/View/Articles/view.ctp, line 116]

Lower Modi Hydro 75 Per Cent Complete

  31 sec to read

The construction work at Lower Modi Hydroelectricity Project is 75 per cent complete. The project at Chuwa VDC of Parbat district is being constructed entirely by Nepali company, technology and investment. The project that began in 2007 is expected to complete by 2011 August.

United Modi Hydropower Pvt Ltd has invested Rs 1.66 billion on the 10 Megawatts project. Upendra Gautam, the Director of the company said, “Construction of headworks, descending basin and canal is 75 per cent complete.” Gautam said if the political environment remains favourable, the project will be completed within the stipulated time period.

Deprecated (16384): Using key `action` is deprecated, use `url` directly instead. [CORE/Cake/View/Helper/FormHelper.php, line 383]
No comments yet. Be the first one to comment.